Some operators use the single large pole placed on cross-ties eight or ten feet apart and use lighter eight-inch poles placed on the outside for a guard rail to keep the truck from leaving the track. The main pole is laid in a ditch about eight inches deep, leaving it half buried. This helps to keep the poles from spreading and increases their firmness and strength. The pole is notched into the cross-ties, which are made of logs not less than eight inches in diameter, and is securely nailed or bolted to prevent it from rolling. The outside guard rail is laid on the surface of the ground close to the main track and is securely braced from the outside by means of posts sunk into the ground or it may be spiked to the main pole or to the ties. When running with the trailer on this narrow type of road, the guard rail is very necessary.
After the poles have been laid, the sub-grade should be ditched in the center deep enough to carry away the water that falls in the middle of the road. The success of the road depends to a large extent upon good drainage.
The Meicklejohn and Brown Logging Company near Monroe, Washington, operate over a pole road with three poles for each wheel. The poles are from ten to twelve inches in diameter at the small end and are hewn to a six inch face, giving an eighteen inch bearing surface for each wheel. (See illustration on page 29.) The minimum sized pole that should be used for roads of this character is one eight inches in diameter at the small end. The road is constructed the same way as the single pole road and the poles are laid on cross ties twelve inches in diameter placed from eight to ten feet apart. Where the road is off the ground as when crossing over a small depression, these sleepers must not be over five feet apart. The guard rails at this operation are held in place by means of a wooden brace nailed from each end of the rail to a near-by stump. The ends of the poles used for the track are adzed so that they match evenly. By breaking the joints and hewing them the road presents a level surface with no bumps.
In planning the curves, it is necessary to make the tracks somewhat wider than on straight stretches in order to keep the trailer from running off. The track should be three feet wide on sharp curves and provided with a stout guard rail if there is any danger of the truck leaving the track. The curves are banked on the opposite side from that used on railroad curves. That is, the inner rail is raised about three inches. This is to throw the load to the outside away from the inner guard rail, making it easier to make the turn without the rear wheels binding. In this way a 35 degree curve may be negotiated with forty or fifty foot logs. As the curves have to be passed at a much reduced speed, there is little danger of the logs rolling off due to the raised inner rail.
The grading for a road of this construction is usually light. The grades should, if possible, be kept below five per cent. A truck will operate better on a ten per cent grade in dry weather than on a five per cent one in wet weather. On a road of this type, grades up to ten per cent can be operated over unless there is snow. When the grades are above this and the weather is wet, traction still may be secured by sanding the road or by tacking an old half inch steel cable to the road in the form of a figure "s". If this is sanded in addition, the truck may safely be taken up a steeper grade than it would be safe to bring it down without sanding.
The pole road could be greatly improved by hewing the faces of the poles where they come together side by side so that an even fit is made. The details of this improved form of construction are shown in figure 1, page 30.
At the present time this is not done and there are one or more ruts in the surface of the road due to the rounding off of the poles where they are placed side by side. The front wheels of the truck are constantly dropping into these ruts, tending to spread the track apart and making it harder for the driver to steer. The tires also suffer from uneven wear. With this deep groove in the track, a certain amount of the traction of the rear wheels is also lost. Hence a much better road would be one with the inner faces of the poles hewn so that a tight fit is secured.
This road can be built of two large poles or three smaller ones to give a flat track two and a half feet wide for each wheel. Laid nearly flush with the ground the guard rail can be eliminated with this width of track, except on sharp curves and other locations where there would be danger if the truck left the track. On such a road the traction will also be increased, better time can be made, the truck will be easier to steer and hence safer to operate, and there will be less wear on the tires. Such a road can be very easily and cheaply built by bringing in a portable sawmill and slabbing the material on two sides to the desired face.
The life of a good pole road is from three to four years if kept in good repair. The maintenance cost is very light if the road is properly constructed in the first place, consisting chiefly in removing a pole here and there that shows signs of too much wear, and in bracing guard rails where they weaken. The use of two or three hewn poles laid lengthwise for each wheel without cross-ties does not pay as the poles soon get out of place even when trenched, and the loss of traction due to the irregularities and of time and money in the upkeep of such a road more than justifies putting in a good road in the first place.
The cost of a fore and aft pole road varies with the accessibility of the material and the cost of the labor. In the past they have been built for as low as $2000 a mile, but with the present prices costs will range from $5000 to $7000 a mile. One company within the year contracted the grading and construction of the road for $70 a hundred foot station, not including the cost of clearing and chunking out the right of way. The total cost was about $125 a station or $6600 a mile.
Some of the advantages of the pole road are that it is tough and strong and does not crack, split or break easily so that if it is properly put in it lasts and requires but little maintenance. The material for its construction is found along the right of way and being small in diameter is less expensive than other road materials.
_Fore and Aft Plank Roads._ This type of road is constructed by placing cross-ties from eight to ten feet apart, center to center, upon which are placed lengthwise for each wheel, two or three sawed timbers not less than six inches in thickness and from twelve to fifteen inches in width. A good road of this type will deliver 150 million feet of logs at a conservative estimate.
The grading is usually light and in many places entirely unnecessary. Second-grade six by eight ties with the eight inch face placed down, or hewn poles are laid about eight feet apart. Where the road bed is soft, the ties are placed closer and in some places as near as two and a half feet apart. Over very swampy ground, the road known as the fore and aft puncheon road is used. It consists simply of cedar puncheon placed crosswise of the road with the usual planking nailed securely to it. The plank used should never be less than six inches in thickness in the main road as it has been proved that four inch plank very soon give way under the heavy loads. On the spur lines it is practicable to use four inch plank because the road is used only a short time.
The total width of the road is eight feet and the plank are laid on top of the ground, but if they are sunk nearly to the level of the ground the road is made considerably more firm and enduring, and of course is safer. The ends are adzed smooth to present an even surface, drift-bolted to the ties, and all joints broken.
The plank in the track are kept together by means of a three by four inch timber driven tightly between the tracks on top of the cross-ties at each joint, and a block nailed to the outside of the tie at each joint with a wedge-shaped piece of wood driven between it and the plank. (See illustration on page 33.) This wedge is driven in from time to time as occasion may demand. If, in addition to this construction, dirt or gravel is filled in the center to the level of the track, the road is made very solid.
With a good road of this type and a bearing surface of thirty inches, the trouble and expense of a guard rail may be eliminated. When a light truck is used for a small body of timber such a wide and heavily constructed road is not practical. In this case, a four inch plank with a fifteen inch surface and an eight inch pole for a guard rail would be used. Here again the track must be made wider on the sharp curves, often as wide as three and a half feet. Usually, the inner rail is made wider than the outer one. On very sharp curves the track may have to be planked solid to keep the trailer from running off. By sawing out chips from one-half to one inch wide two-thirds of the way through the plank, and about six feet apart on the inner side, a long plank may be bent around quite a sharp curve. The ties, of course, should be placed so as to allow the cut sections of the plank to rest squarely on them. This does away with the short pieces and so strengthens the track.
The company logging at Camano Island, Washington, operates over a road of this type, an illustration of which is shown on page 38. The difficulties encountered in the construction of this particular road were very considerable as a cut through very hard shale, in some places as much as seven feet, was necessary. The maintenance on this road is heavier than is usual. Two men are employed to work on it continually. The work consists of blocking up the loose ties and plank, making any necessary repairs and keeping sand and gravel on the steep grades. The cost of this work is good insurance as it keeps the road in the best of condition at all times and saves on other operating expenses.
_Cost._ The first cost of a road of this type is high but it more than pays in the long run if a large body of timber is to be hauled over it. The timber used in its construction amounts to about 160 thousand feet per mile. Second grade material can be used at a cost of approximately $5,500 a mile for the plank. The total cost per mile varies from $6,000 to $8,000. The plank road at Camano Island cost $20,000 for two and three-quarter miles, which includes the cost of the plank, the grading and labor of putting the plank in place. This is at the rate of about $7,275 a mile, or approximately $138 a hundred foot station. The overhead charge for the road at this operation is $.75 a thousand feet of timber hauled over it. Plank roads of lighter construction have been built for $4,000 a mile. The length of life is about the same as that of a pole road, three to four years.
The fore and aft plank road is one of the best roads that can be put in where the timber is of sufficient quantity to justify the expense. The big advantage is the speed that can be made and the saving in the equipment. Such a road is very free from bumps and the jar and vibration on the truck is no greater than on a city pavement. The depreciation on a truck depends to a great extent upon the road operated over. With the above type, depreciation on the truck will not be less than five years. In addition, tire mileage will be double that obtained over a pole road, and the gasoline and repair expense will be very materially cut. Owing to the very small vibration, a load of logs can be brought to the landing as fast as it is safe to let the truck glide on a down grade. Speeds as high as 20 miles an hour can easily be taken without excessive vibration. The traction is greater on this type of road than it is on the pole road, due to the greater bearing surface. Traction on grades up to 12% is easily secured by sanding the plank.
_Concrete Roads._ Concrete has been suggested as an ideal road material. However, up to the present time, loggers have not been very enthusiastic about this type of road on account of the cost of construction, which is somewhat more expensive than the other types of roads, and on account of the permanence of the finished road which is beyond that needed. To the writer's knowledge, there is no company operating in the Northwest over a concrete road of their own building. In the future such roads may be used to a limited extent on the main haul by companies which have operations extending over at least a five year period. The spur roads will probably always be of some other material.
In building such roads two tracks of concrete, one for each wheel are provided. The sub-grade should be well ditched in the center with cross ditches every fifty feet, as is done with the pole road. It has been suggested that the ditches holding the track be six inches deep and twenty-six inches wide. They are filled to the top with concrete and built with a lip four inches high and four inches wide along the outside on top of the main surface to serve as a guard rail. No forms are necessary except for the guard lip.
A word of caution here may not be amiss. Concrete roads of this nature must be regarded as only experimental, for no specific data are available for determining the proper section of concrete to be used for carrying heavy loads on so narrow a bearing surface. It is evident that the carrying capacity of such strips of concrete would be greatly affected by the character of the sub-base. It will therefore be impossible to specify a standard that can be used under all conditions.
The use of the concrete guard rail is one of the disadvantages of this road. The edges of the rail cannot be made rounding except by special forms and the rubbing of the tires against this rough surface would greatly reduce the tire mileage. In addition, the rail is so exposed to weather and hard wear that it cannot be relied upon to serve effectively for any great length of time. The placing of forms is also a considerable item of expense in building such a road. A method which would eliminate such an expense and at the same time provide a more practical rail would be an advantage.
It has already been said that guard rails are unnecessary with a thirty inch track except on sharp curves and otherwise dangerous places. However, where rails are necessary the wooden rail fastened by bolts embedded in the concrete as illustrated above, is quite effective and readily installed. This consists of a four by six inch plank placed on edge and drift-bolted to the concrete every three to five feet by a three-quarter inch bolt. These bolts are placed in the concrete when it is poured and should be embedded six inches. This will provide a rail less expensive to build than a concrete rail and one which will last longer and save on tires. Replacements are easily made by removing the nuts and placing a new plank in place of the old. With a guard rail of this type, there is left a twenty-six inch track for the wheels to run in.
Experiments by W. D. Pence (Journ. West. Soc. Eng. Vol. VI, 1901, Page 549) on 1:2:4 concrete give an average value of 0.0000055 inches per degree Fahrenheit for the coefficient of expansion. The richer the concrete, the greater the change in dimension. Due to the expansion, in laying the concrete the track must be broken every twenty-five or thirty feet by placing a half-inch board in the ditch when the concrete is being filled in. Later this board is removed and the joint filled with asphalt so that the concrete may expand without danger of cracking the road.
_Cost._ The best mix to use in building this road is what is known as the 1:21/2:5. For one cubic yard of concrete, the following amounts of materials will be used for the above mix: 1.21 barrels of cement, 0.46 cubic yards of sand, and 0.92 cubic yards of stone. At the present prices, the cost for the materials for this road is about twenty cents a cubic foot or about $4,400 a mile. The total cost of the road including the necessary grading, ditching and labor, will be from $7,000 to $9,000 per mile.
One of the big advantages of the concrete road is the large gain in traction secured when operating on steep grades. A motor truck will haul up a twelve per cent and down a fifteen per cent grade in wet weather on concrete due to the roughened surface on which the tires do not easily slip. This, of course, would be dangerous to attempt on the other types of roads. Another advantage is the small item of upkeep necessary. A road well laid in the first place should need no repair except to replace worn guard rails as they show signs of weakening. The concrete road, however, will not be generally used except on the mainline by the larger concerns, or for short distances on steep grades where greater traction is desired.
BRIDGES
In most cases the construction of bridges is unnecessary on account of the steep grades the trucks can take and because they can negotiate sharp curves, which make it easier to avoid expensive bridge work. Where they are absolutely necessary a serviceable bridge is made of cribwork.
The Esary Logging Company of Camano Island, Washington, operates over a crib bridge 175 feet long and 15 feet high. The sub-structure of this bridge is made of logs laid alternately crosswise in tiers. Six by twelve inch plank are laid diagonally on the cribbing and four by twelve inch plank are placed on crosswise to the road on top. This makes a bumpy surface. A better one could be made with cross-ties placed on the cribbing with fore and aft planking on top. A guard rail is placed on all bridges.
Short bridges up to eighty or ninety feet in length are constructed by the use of two large logs hewn flat on the upper surface. The logs should be at least thirty-six inches in diameter and perfectly sound. They are placed at the proper gauge and the regular road on cross-ties constructed on top. On such short stretches this type of bridge has been operated over without supports. It is not used, however, for long stretches. The long bridges are, of course, constructed of bents or piling but are very seldom used in connection with motor truck transportation on account of the expensive construction and because they are usually unnecessary.
TURNING DEVICES AND TURNOUTS
When the truck and trailer reach the place where they are to be loaded, some method must be used to turn them around. Various means are used to accomplish this. One is the motor truck turn-table. The turn-table should be slightly longer than the length of the truck and trailer combined. It is constructed of heavy plank and timbers so that each track is about 16 inches wide and tapers in thickness from about 14 inches at the center to 4 inches at the ends. The two tracks are held together at the center and each end by heavy timbers. A heavy timber is sunk to the level of the road and at the center two circular saws are laid. A king bolt through the center brace of the turn-table and through the two saws into the sunken timber provides a pivot upon which the table turns. When properly balanced and with a little oil between the surfaces of the saws, the turn-table can be operated by hand with very little effort. It is usually placed at the end of the road. A turn-table can be loaded on the truck and trailer when it is desired to move it, so that as the road is extended into the timber, a means of turning the truck can be obtained close to the point where the logs are to be loaded. This device can be built at a cost of from $75 to $125 and is very serviceable. The main objection to its use is that the setting has to be just right to make it work satisfactorily and it is sometimes difficult to get a spot that is level enough. It is always a difficult problem and a different one for each set-up.
The use of the "back around" is more common with truck loggers at present because it is easier to build. The back-around is simply a pocket or short spur along the road above the landing ground which is planked solid. The truck and trailer are backed into this far enough so that the truck can pull ahead in the opposite direction. This method of turning the truck requires only a little extra clearing and grading and is less expensive and more easily constructed than a turn-table.
When two or more truck units are to be used on a single track, a careful calculation must be made to determine the best passing places. The location of these points may determine the success of the operation. They should be placed so that the truck returning empty can reach the turnout before the loaded one comes along in order that the loaded one may not be held up. At the same time, the turnout should not be so far away from the loading ground that the loading crew will be idle for any length of time while waiting for an empty truck. It is better to have an extra turnout, even if seldom used, than conditions that would hinder efficient operation or might even result in a collision which would tie up the logging for several days.
A few loggers build a turnout of the same material as the main road for a short distance to the side. An illustration of this type of turnout is shown above. Most of them, however, simply clear off a right of way and put in a gravel bottom for the road as the waiting truck at this point is empty and will not ordinarily sink into the ground and get stalled. A few heavy planks laid fore and aft in the form of a track are sometimes used. The construction of passing places is very simple--the only important thing to be taken into consideration is the proper point at which the trucks should pass in order to keep the operation going at maximum efficiency.
TELEPHONES
In connection with the passing places, the installation of a telephone line is an important but often neglected item. With two or more transportation units, a telephone line is a handy if not well nigh indispensable accessory. It is a great advantage to have such a system with stations at each end of the road and also at the passing places, as unavoidable delays will frequently allow a waiting truck to move on to another passing place, thus saving time. To avoid accidents, the driver at the passing place should call the loader at the spar tree to see if the road is clear before coming any farther.
Very often something breaks on the yarding or loading donkey. With the telephone, perhaps a half day of shutdown may be saved by calling the main camp for the repair parts and having them brought up by the next truck. The saving due to avoided accidents and the saving of time more than pays for the initial expense of installation. The telephone line should not be neglected at the larger operations.
INCLINES
In rough country the use of the incline has been a great help and has proved to be entirely practical and quite economical. Grades as high as sixty or even seventy per cent can be safely taken with an incline if the proper measures are taken to prevent accidents.
A typical incline is successfully operated by the Meickeljohn, Brown Logging Company near Monroe, Washington. It is fifteen hundred feet long and the steepest grade is twenty-eight per cent. An 11-in. x 14-in. roader donkey located at the top of the incline snubs the loads down and hauls up the empty trucks. A one and one-eighth inch wire cable is thrown around the logs and made fast by means of a clevis. This holds the truck and prevents the logs from slipping forward and injuring the driver. On all inclines, the line should be choked around the logs rather than simply attached to the truck to prevent them from slipping ahead.
The snubbing device consists of an ordinary donkey engine fitted with a hand brake of extra large size and special air valves so that air is sucked into the cylinders and let out of the exhaust when the engine is being pulled backwards by the weight of the load. The load is controlled by the amount of air let out of the valves. The braking action is very positive and the load can be stopped in a few revolutions of the crank shaft.
The average time to lower the load down the incline is three and a half minutes. At the bottom of the incline, the cable is released and the truck goes on its way. The cable is attached to the waiting truck by means of a ring fastened to the frame and the donkey pulls the empty truck to the top. The time taken to raise the trucks is three minutes.
On grades too steep to operate a truck safely with the ordinary brakes and yet not steep enough to warrant the expense of the donkey snubber, the difficulty is overcome by means of a friction snubber. This consists simply of a cable which is hooked to the truck and extends through a system of three or four pulleys and thence on down the track. The friction of this line dragging on the ground and passing through the pulleys is enough to hold the load so that the truck engine must exert power to pull the load down the grade. The line is made long enough so that as the load reaches the bottom of the grade, the free end of the cable has been pulled up to the system of pulleys and is ready to be attached to the next load. This system is efficient for small grades, is inexpensive to install, and requires no further attention.
By the use of the incline with the donkey engine snubber, very heavy grades can be taken. The construction of the incline is the same as the rest of the road and is only slightly more expensive to build because of the inconvenience of laying it on such a steep slope. The use of the incline will not slow up the operation to any great extent as from fifty to seventy thousand feet of logs (which is about the average yarding and loading capacity of one motor-truck side), can be taken over it in a day. This method of hauling down steep grades is used in several operations and has been found to be entirely successful.
YARDING
A variety of methods are used by motor truck loggers to get the logs to the landing to be loaded. The larger operations invariably use the high-lead method of yarding as the logs come in quicker and with fewer hang-ups. In a few places the old ground method of yarding with a bull block is still used. The horse team and skid road is used in a small timber where poles and piling are being marketed. The latter is a slow method but will keep one truck busy and is still used in some places where small stands are located along the highway or in other readily accessible places.
LOADING AND UNLOADING
The loading of a motor truck is very much the same proposition as the loading of a flat-car. The principal difficulties that trucks have had to contend with have been poor roads and inefficient methods of loading. In loading, the main trouble has been in regulating the yarding so that a supply of logs is always on hand. The use of the gin pole and crotch line operated by the straw drum of the yarding donkey ties up the yarding until the truck is loaded. This is being overcome by using a separate engine with the high lead for yarding and doing the logging independently of the yarding as is done in the case of railroad logging. In this way the yarder can keep ahead of the loading engine and there will be no delay at the landing.
Most of the larger companies load with the Duplex loader and use tongs. This is a safer way to load than with the crotch line as the logs can be more easily controlled. The danger of dropping a log through the truck or of knocking off the top of the truck or the driver's seat is greatly lessened.
In pole and piling timber where a skid road and horses are used, loading is done by hand or with a team. A landing is built of cribwork and the logs are simply rolled on the truck with peavies or cant hooks, or a parbuckle system with skids and horses is used. This works fairly well for small operations in small timber.
The latest development in loading is the boom. An illustration of this method is shown above. The boom itself is a fifty to sixty foot pole about eighteen inches in diameter at the base and is attached to the spar tree by means of a metal strap with two lugs which are fitted into holes bored in the spar to keep the strap from slipping. The base of the boom is fitted with a metal joint which moves freely on an upright pin set in the metal strap. (See A, above.) The whole rig is set high enough on the tree so that it may be swung in a semi-circle and clear the loaded truck by several feet. A light line (B) from the haulback drum of the donkey passes through a block attached low on the spar tree and thence to another block on a stump to the right of the landing. From here it passes through a third block at the end of the boom and back to the stump again. This secures the needed pulling power from the haulback drum.
The lifting line from the mainline drum passes through a block half way up the tree and thence through a free swinging block (C) and back to the tree again. On the second block is a ring to which two one inch lines (D) are attached. These lines pass through the boom stick on rollers (E) about fifteen feet apart. On the ends of these lines hooks are attached. These two lines should be so arranged that the hooks remain parallel to the ground. Two three-quarters inch cables (F) with an eye splice in each end are attached to the hooks. These lines, or chokers, are then wrapped around the log and it is lifted clear of the ground by means of the block hold in the main line.
The haulback line (B) from the donkey is slacked and the boom travels over to the truck by means of a line (G) attached from the boom to a dummy log running on a special guy line. A log two feet in diameter and sixteen feet long is wrapped at each end with a cable and fastened to a pulley. The two pulleys and attached dummy log travel up and down the guy line as the boom moves. A line is attached to the boom and runs through a pulley attached to the dummy log and extends back to the boom again. This pulls the boom over above the truck as the dummy log travels down the guy line. The logs are held parallel to the ground above the truck and the truck is run under the boom to the location designated by the head loader. With this system the logs will not drop suddenly on the trucks as the log will fall off while being carried over to the truck if there is any danger of its falling at all. After the log is placed, the boom is pulled back to the landing by the haulback line. This system has worked with success in a number of motor truck operations and is a safer method than loading with tongs because the logs cannot accidentally drop and injure the truck. However, the loading situation should be studied carefully. The most efficient loading device for the particular needs of the operation may be installed as any loss of time in loading seriously affects the output of the operation.
Most of the truck loggers unload their logs into water; either into a lake, a river that can be driven, or into tide-water. A few, however, unload directly into the log pond at the mill or at the log yard in case the mill has no log pond.
The road is usually planked solid at the unloading ground. A great help in unloading is a dock from six to twelve inches higher on one side than on the other so the logs will roll off the truck easily. The brow-skid should be close to the log bunks and just a little lower than these when the truck is tilted. When unloading into shallow water, such as a small river, six or eight skids a foot and a half in diameter are placed so that they slope from the brow-skid to the water at an angle of forty-five degrees. An illustration of this method of unloading is shown below. The skids are so placed that the unloading ground will not be undermined.
When the truck comes to a stop on the incline, the chock blocks are released from the opposite side and the logs roll off of their own accord. In some instances a gill-poke has been used in connection with the unloading incline, the logs being sheared off as the truck moves ahead. Usually the logs roll off readily without the use of the gill-poke and if a load does stick it can be loosened with a cant-hook, so that the gill-poke really is unnecessary.
Unloading on public wharves or roads where no permanent incline can be used is accomplished by placing a portable wedge-shaped timber in front of the outside truck and trailer wheels and driving upon it.
In the most efficient way of unloading the usual brow-skid is placed a few inches below the log bunk and the logs are parbuckled from the truck and trailer, an illustration of which is shown above. The trucks are run on an incline so that one side is raised about four inches. A crotch-line consisting of two half-inch cables is attached to the brow-skid and passed under the logs to a ring fastened to an inch cable. The larger cable passes thru a block located on a gin pole. A light yarding or a land clearing donkey furnishes the power to parbuckle the logs into the water. By this method the logs are lifted from the truck as they are rolled into the water with little danger of the top log dropping on the log bunk as is often the case when other methods are used, resulting in expensive repairs for broken springs or bearings.
TIME STUDIES
Time is a very important item in loading and unloading. Usually the most time is consumed in loading, for which reason any improvement that will reduce the time taken to load will greatly increase the efficiency of the operation. With the proper unloading devices, the truck may be unloaded in the time required to knock down the chock blocks.
The following table is a record kept for one day of the actual time taken by a truck at each step in the hauling of logs at one operation. However, it is possible to give only arbitrary figures to fit the particular operation of which they are taken. No average figures can be given that fit all conditions.
DONKEY ENGINE DUMP AT MILL
Time Time Unload- Time
Arrive Loading Leave Down Arrive ing Leave Up Scale
A.M.
7:15 10 Min. 7:25 20 Min. 7:45 25 Min. 8:10 20 Min. 2592
8:30 5 Min. 8:35 27 Min. 8:57 13 Min. 9:10 20 Min. 2092
9:30 12 Min. 9:42 21 Min. 10:03 7 Min. 10:10 20 Min. 1908
10:30 12 Min. 10:42 33 Min. 11:15 30 Min. 11:45 20 Min. 3074
P.M.
12:05 10 Min. 12:15 35 Min. 12:50 17 Min. 1:07 20 Min. 2542
1:27 15 Min. 1:42 18 Min. 2:00 27 Min. 2:27 20 Min. 1828
2:47 8 Min. 2:55 21 Min. 3:16 8 Min. 3:24 20 Min. 1689
3:44 11 Min. 3:55 23 Min. 4:18 9 Min. 4:27 20 Min. 2407
4:47 14 Min. 5:01 26 Min. 5:27 12 Min. 5:39 20 Min. 2558
-----
Total 20690
Length of haul 5.9 miles round trip.
Amount of gasoline, 15 gallons.
The above figures were taken several years ago when the facilities for unloading were slower than the present day methods, which accounts for the excessive length of time taken to unload.[8]
[8] The writer is indebted to Mr. George Gunn, Jr., for these figures.
The unloading of a truck is a time when a little care taken will save considerable expense for repairs. Such a method as the parbuckling system should be used by companies with sufficient stumpage to warrant the expense of the extra donkey, to prevent the top logs from dropping to the log bunks, thereby saving the cost of repairing broken springs and bearings.
CONCLUSION
At present, the possibilities for the use of the motor truck for logging are just beginning to be realized. What effect their use will have upon the future methods of logging remains to be seen. It is certain, however, that the advent of motor truck transportation will have a marked effect upon the science of forestry and will bring about a closer utilization of our timber resources.
The motor truck and the portable band mill seem likely to furnish a combination which will do away with the old wasteful circular mill because it supplies the cheapness and efficiency of railroad transportation and is applicable to small and scattered tracts and to stands of low-grade lumber. The fact that the portable band mill may be moved for a cut of a million feet assures adaptability. This is not only an industrial advance but also a silvicultural advance in that it affords the possibility of cuttings at frequent intervals without greatly adding to the cost.
A closer utilization of our present stands of timber may be practiced by the use of the motor truck. In the northwest, only the larger material is taken from the forest, leaving a large amount of good timber on the ground in the form of poles and piling and chunks too short to be made into saw lumber but from which high grade ties can be made. The truck, in connection with a band mill, will furnish a means of utilizing this present waste at a profit to the operator.
The motor truck will be a valuable aid in the working out of a sound national forest policy for the proper use of our timber resources so that the timber will be utilized to the greatest possible extent and at the same time methods taken to provide for the perpetuation of the forest for future generations. This suggests a way of opening the timber for the market on some of our national forests. Most of the government owned forests are situated in more or less rugged country back from the regular routes of travel. The timber on a great many of these forests is over-mature and should be cut but at this time it is inaccessible. The problem confronting the country is how to make it accessible.
The plan for opening these forests is to build permanent concrete or asphalt roads from the nearest commercial centers thru these tracts taking into consideration the aesthetic value of the location as well as the possibilities of logging the timber from them. The timber, then, is to be taken out, under some silvicultural system and under government supervision, by motor truck operators who build their own roads from the nearest concrete road to the timber to be cut. Under this system of management, the state and federal government pays a part of the expense of building the permanent road and the operator pays a small sum for the use of the road by being taxed additional stumpage.
The system of management has many advantages. In the first place, the mature timber will be logged, the older decadent material coming out first, in small bodies and at the same time care being taken to reproduce a new stand. The total area is divided so that as the timber is logged in rotation a continuous cutting will be assured. Due to the use of the trucks and on account of the timber being cut in rotation, the fire danger will be greatly lessened. In case a fire gets beyond control, the roads thru the forest make an excellent way to bring in men and supplies to fight the fire. In this way, a fire is readily accessible in a few hours where formerly it took perhaps several days to organize the fire fighting party and reach the scene of action. The concrete roads themselves make good fire lines. By means of the good roads, the forest is opened to campers and tourists each of whom pays a small sum as they enter the forest to help pay for the cost of building the roads and to provide funds for more extensive highways. In this way the forest is opened for the timber, the best methods of utilization and forest regeneration are practiced, fire hazard is reduced, and the area is opened as a recreational ground so that the greatest possible value is obtained from the tract.
A great many other uses of the motor truck for logging and scientific forest utilization are being recognized, as example, for transporting pulpwood, veneer stock, cordwood, rosin and turpentine, and other forest products. Suffice it to say that this method of transportation has found a place in the industry and is here to stay. Its value has been recognized beyond doubt and in the future will play an important part in the further development of this country.
BIBLIOGRAPHY
1916. Motor Truck Logging.
The Power Wagon. Sept. 15. Page 34. (Periodical).
1916. The Law of the Public Highway in Washington.
West Coast Lumberman. Sept. 15. Page 23. (Periodical).
1916. Motor Truck Logging Now Making Great Strides on the Pacific
Coast. West Coast Lumberman. Nov. 1. Page 260. (Periodical).
1917. Motor Truck Logging in the Pacific Northwest.
West Coast Lumberman. Mar. 15. Page 70. (Periodical).
1917. Motor Trucks in High Favor Among Lumbermen.
Lumber World Review. Mar. 25. Page 23. (Periodical).
1917. Motor Truck Logging on Camano Island.
West Coast Lumberman. July 1. Page 28. (Periodical).
1917. Motor Truck Logging.
The Commercial Vehicle. Sept. 1. Page 12. (Periodical).
1918. Pole Roads. A. R. Hillard.
West Coast Lumberman. Feb. 1. Page 34. (Periodical).
1918. Operating Cost of Motor Trucks Computed. H. S. Finch.
Timberman. Feb. 1. Page 60. (Periodical).
1918. Winch for Motor Trucks.
American Lumberman. Mar. 2. Page 58. (Periodical).
1918. Motor Truck Roads.
American Lumberman. Mar. 16. Page 38. (Periodical).
1918. The Motor Truck in the Logging Industry. H. H. Warwood.
Timberman. April 1. Page 74. (Periodical).
1918. Road Construction for Motor Trucks. Jay C. Smith.
Timberman. April 1. Page 38. (Periodical).
1918. Adjustable Reach Logging Trailer.
American Lumberman. May 18. Page 63. (Periodical).
1918. Demonstrating Duplex Trucks.
American Lumberman. June 1. Page 63. (Periodical).
1918. Modern Motor Truck Solves Difficult Logging Problems.
West Coast Lumberman. July 1. Page 18D. (Periodical).
1918. Motor Trucks in Winter Logging. A. R. Hilliard.
West Coast Lumberman. Sept. 1. Page 25. (Periodical).
1919. The Effect of Changed Conditions Upon Forestry. W. W. Ashe.
Journal of Forestry. Oct. 1. Page 657. (Periodical).
1919. Puget Sound Logger Tells Congress How to Log With Motor Trucks.
West Coast Lumberman. October. Page 25. (Periodical).
1920. Air Brakes for Trucks.
Timberman. Mar. 1. Page 48g. (Periodical).
The writer has drawn freely from the material found in the above periodicals and trade journals, but wishes to acknowledge the greater bulk of information in writing this paper received from the various truck salesmen and truck operators who were interviewed personally. Without their assistance, the gathering of this information would have been impossible.
Publications of the Engineering Experiment Station University of Washington
=Bulletin No. 1=--Creosoted Wood Stave Pipe and Its Effect Upon Water
for Domestic and Irrigational Uses. 1917.
(Bureau of Industrial Research.) 20 pp. Price, 25 cents.
=Bulletin No. 2=--An Investigation of the Iron Ore Resources of the
North-west. By William Harrison Whittier. 1917.
(Bureau of Industrial Research.) 128 pp. Price, 60 cents.
=Bulletin No. 3=--An Industrial Survey of Seattle. By Curtis C. Aller.
1918.
(Bureau of Industrial Research.) 64 pp. Price, 50 cents.
=Bulletin No. 4=--A Summary of Mining and Metalliferous Mineral
Resources in the State of Washington with Bibliography.
By Arthur Homer Fischer. 1919. 124 pp. Price, 75 cents.
=Bulletin No. 5=--Electrometallurgical and Electrochemical Industry
in the State of Washington. By Charles Denham Grier.
1919. 43 pp. Price, 50 cents.
=Bulletin No. 6=--Ornamental Concrete Lamp Posts. By Carl Edward
Magnusson. 1919. 24 pp. Price, 40 cents.
=Bulletin No. 7=--Multiplex Radio Telegraphy and Telephony. 1920.
By F. M. Ryan, J. R. Tolmie, R. O. Bach. Price, 50 cents.
=Bulletin No. 8=--Voltage Wave Analysis with Indicating Instruments.
By Leslie Forrest Curtis. 1920. 28 pp. Price, 50 cents.
=Bulletin No. 9=--The Coking Industry of the Pacific Northwest.
By Joseph Daniels. 1920. 36 pp. Price, 60 cents.
=Bulletin No. 10=--An Investigation of Compressed Spruce Pulleys.
By George Samuel Wilson. 1920. 72 pp. Price, 80 cents.
=Bulletin No. 11=--The Theory of Linear-Sinoidal Oscillations.
By Henry Godfrey Cordes. 1920. 24 pp. Price, 40 cents.
=Bulletin No. 12=--Motor Truck Logging Methods.
By Frederick Malcolm Knapp. 1921. 52 pp. Price, 50 cents.
Requests for bulletins should be addressed to the Director, Engineering Experiment Station, University of Washington, Seattle.
<pre id="pg-footer">
Comments
Log in to leave a comment.
Motor Truck Logging MethodsChapter II: Part 2
0%33 min left in chapter